Thanks to everyone who has offered feedback on the website. We've corrected a couple of typos and we are starting work on the secondary links, the ones at the bottom of each page. We'll be adding some pictures and other information to those pages. We appreciate your input, so if there is anything that you like --- or hate --- about the site, let us know.

- Glenn

Building Addition

Construction has started and we're shooting for an August completion. The permitting process was a bit more complicated than it was seven years ago when we constructed a 20,000 addition to our existing building. That resulted in a three month delay in our overly optimistic projected October start. Things are moving along now, though. We've started the sitework and will continue with it through the winter months as long as the weather cooperates. When completed the 64,000 square feet addition will bring our total manufacturing space in Tipton to 144,000 square feet.

- Glenn